下記の製品の出荷の可否について、下記の通り決定する。
評価した結果、内容に逸脱はありましたか?あり/なし
逸脱があった場合の措置は適切ですか?適切/不適
製造所からの出荷の可否について。可(承認する)/否(承認しない)
決定年月日(Date of decision)と決定者。
Translation / English
- Posted at 12 Nov 2013 at 16:12
We will determine the shipment of the following products as follows.
As a result of the evaluation, were there any deviation in the content? Yes / No
If there is a deviation, is the measurement appropriate? Appropriate / inappropriate
Will you approve the shipment from the manufacturing plant? Yes (approve) / No (not approve)
Decision date (Date of decision) and the person who made the decision
shivai likes this translation
As a result of the evaluation, were there any deviation in the content? Yes / No
If there is a deviation, is the measurement appropriate? Appropriate / inappropriate
Will you approve the shipment from the manufacturing plant? Yes (approve) / No (not approve)
Decision date (Date of decision) and the person who made the decision
Rating
52
Translation / English
- Posted at 12 Nov 2013 at 16:07
This is to certify that we have decided the shipment of below as follows;
1) Has the evaluation revealed the deviation in the contents? (Y/N)
2) Has the countermeasure for the deviation appropriate? (Y/N)
3) Shipment permission of the manufacturing factory (Approved/Not approved)
Date of decision:
Person responsible for the deision:
shivai likes this translation
1) Has the evaluation revealed the deviation in the contents? (Y/N)
2) Has the countermeasure for the deviation appropriate? (Y/N)
3) Shipment permission of the manufacturing factory (Approved/Not approved)
Date of decision:
Person responsible for the deision:
Translation / English
- Posted at 12 Nov 2013 at 16:08
About possibility of shipment of the following products, decide as follow.
Is there any deviation or evaluated result? Yes/No
The measurement in case of deviation is suitable or not? Yes/No
About possibility of shipment from the factory. Yes (Approval)/No (Not approval)
Date of decision (Date of decision) and name of the person who made a decision
Is there any deviation or evaluated result? Yes/No
The measurement in case of deviation is suitable or not? Yes/No
About possibility of shipment from the factory. Yes (Approval)/No (Not approval)
Date of decision (Date of decision) and name of the person who made a decision