1個流し生産と後工程引き取り
ダンゴ生産
仕掛品がたくさん必要
1個流し生産と後工程引き取り
外れたかんばんで前工程へ取りに行く
引取りに行った前工程ストアで仕掛けかんばんと差し換える
後補充生産時の“かんばん”の流れ
KNで加工・組付けされる部品
現品票をQRカードに差し換え
直送品
NKから直接車両メーカへ納入される部品
QRカードを客先かんばんに差し換え
日程管理部署
現品明示票
現品に添付移動
生産実績計上用
メーカー納品用
後補充生産
後補充かんばん
直送支給伝票
客先かんばん
毎日1回 夜中PCデータ入手
Translation / English
- Posted at 25 Apr 2015 at 09:30
One-Piece-At-a-Time Production and Pull System(of Production)
Mass-production
Need many work in progress
One-Piece-At-a-Time Production and Pull System(of Production)
By seeing a removed kanban, pick up items to the earlier process
At the earlier process, replace the kamban placed to Production (P) Kanban:
The flow of "Kanban" in the Fill-Up System(of Production)
Parts processed and assembled at KN
Replace identification tags to QR cards
Direct Sent Items
Parts delivered directly from NK to car manufacturers
Replace QR cards to cutomer kanban
Schedule management department
identification tags of actual articles
Attach to the actual articles and move
For production result input
For the delivery to manufacturers
Fill-Up System(of Production)
Fill-Up System kanban
Direct delivery supply voucher
Client kanban
Obtain data once a day(mid-night)
akaraage likes this translation
Mass-production
Need many work in progress
One-Piece-At-a-Time Production and Pull System(of Production)
By seeing a removed kanban, pick up items to the earlier process
At the earlier process, replace the kamban placed to Production (P) Kanban:
The flow of "Kanban" in the Fill-Up System(of Production)
Parts processed and assembled at KN
Replace identification tags to QR cards
Direct Sent Items
Parts delivered directly from NK to car manufacturers
Replace QR cards to cutomer kanban
Schedule management department
identification tags of actual articles
Attach to the actual articles and move
For production result input
For the delivery to manufacturers
Fill-Up System(of Production)
Fill-Up System kanban
Direct delivery supply voucher
Client kanban
Obtain data once a day(mid-night)
Translation / English
- Posted at 25 Apr 2015 at 10:25
“One-piece flow” technique production and pull system
"Dango" production (lot production)
A lot of half-finished products are needed
“One-piece flow” technique production and pull system
Pull at the previous process by the detached kanban
Replace with production instruction kanban at the previous process store one goes for pulling
Kanban flow at the time of fill-up production
Parts worked and assembled in KN
Replace QR card with client identification tag
Direct delivering products
Parts delivered to vehicle maker directly from NK
Replace QR card with client kanban
Schedule control section
Explicit identification tag
Attach it to the product on display and move
Products for production result input
Products for maker delivery
Fill-up production
Fill-up kanban
Direct delivery supply slip
Client kanban
PC data acquisition at midnight once a day
akaraage likes this translation
"Dango" production (lot production)
A lot of half-finished products are needed
“One-piece flow” technique production and pull system
Pull at the previous process by the detached kanban
Replace with production instruction kanban at the previous process store one goes for pulling
Kanban flow at the time of fill-up production
Parts worked and assembled in KN
Replace QR card with client identification tag
Direct delivering products
Parts delivered to vehicle maker directly from NK
Replace QR card with client kanban
Schedule control section
Explicit identification tag
Attach it to the product on display and move
Products for production result input
Products for maker delivery
Fill-up production
Fill-up kanban
Direct delivery supply slip
Client kanban
PC data acquisition at midnight once a day
翻訳ありがとうございました。