Conyac で依頼された翻訳結果を公開
[英語から日本語への翻訳依頼] 過電流保護デバイスと切断手段を通して配線ポイントからケーブルをACインターフェイス接続の所定の配管入口部分へ配線します。 装置接地コンダクタを保護ア...
翻訳依頼文
Route the cables from the grid connection point through the overcurrent protection device and means of disconnect to the prepared conduit entry location for the AC interface connection.
Connect the equipment ground conductor to the Protective Earth ground connector (M10 ground stud). Torque the connection to &GNDTorque
Connect the appropriate phase connections to the three AC phase connectors, labeled
Torque each connection as shown in the table below
The unit detects AC phasing, and matches it at startup. If the phasing changes during operation, a phase sequencing fault displays on the digital display.
Connect the equipment ground conductor to the Protective Earth ground connector (M10 ground stud). Torque the connection to &GNDTorque
Connect the appropriate phase connections to the three AC phase connectors, labeled
Torque each connection as shown in the table below
The unit detects AC phasing, and matches it at startup. If the phasing changes during operation, a phase sequencing fault displays on the digital display.
gloria
さんによる翻訳
過電流保護デバイスと切断手段を通して配線ポイントからケーブルをACインターフェイス接続の所定の配管入口部分へ配線します。
装置接地コンダクタを保護アースグラウンドコネクター(M10グラウンドスタッド)に接続します。配線を&GNDトルクにトルクを合わせます。
適切なフェイズ配線をラベルのついた3つのACフェイズコネクタに接続します。
各配線を下の表のようにトルクを合わせます。
ユニットはAC位フェイズ整合を検知してスタートアップに合わせます。作動中にフェイズが変化すると、デジタル表示部にフェイズシーケンス障害と表示されます。
装置接地コンダクタを保護アースグラウンドコネクター(M10グラウンドスタッド)に接続します。配線を&GNDトルクにトルクを合わせます。
適切なフェイズ配線をラベルのついた3つのACフェイズコネクタに接続します。
各配線を下の表のようにトルクを合わせます。
ユニットはAC位フェイズ整合を検知してスタートアップに合わせます。作動中にフェイズが変化すると、デジタル表示部にフェイズシーケンス障害と表示されます。